Exambible offers free demo for 70-499 exam. "Recertification for MCSD: Application Lifecycle Management", also known as 70-499 exam, is a Microsoft Certification. This set of posts, Passing the Microsoft 70-499 exam, will help you answer those questions. The 70-499 Questions & Answers covers all the knowledge points of the real exam. 100% real Microsoft 70-499 exams and revised by experts!
Q41. DRAG DROP - (Topic 2)
Your team uses Microsoft Test Manager (MTM) to manage test cases. You have a test plan with test cases organized in multiple test suites. You add a new configuration and associate it to your test plan.
You need to include the new configuration in a test suite as part of the default configurations.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Q42. - (Topic 2)
You are running a manual test using Microsoft Test Manager (MTM). You have chosen to
create an action recording.
You want to pause the test run and exit the test runner.
Before you exit the test runner, you need to mark the test case as being in progress.
Which action should you perform in the test runner?
A. Close
B. Return to Testing Center
C. Save
D. Save and Close
Answer: B
Q43. - (Topic 3)
Your development team uses Scrum as its process framework and utilizes the Microsoft Framework (MSF) for Agile Software Development 6.0 process template.
A new team member who is new to Scrum assumes the role of product owner.
You need to help the new product owner prioritize the product backlog.
Which basis should you suggest the new product owner use for prioritizing the product backlog?
A. personal preference
B. estimated cost and effort for each requirement
C. risk and business value of each requirement
D. technical complexity of each requirement
Answer: C
Explanation: In other words, it’s more important to deliver business value in the form of working software than to follow a plan.
Professional Scrum Development with Microsoft Visual Studio 2012 p.162
Q44. - (Topic 3)
You are part of a scrum team that is trying to identify user stories to complete in the next sprint.
You and the team need to select user stories for the next sprint.
What should you do?
A. Have the product owner decide which user stories to complete within the sprint.
B. Have the scrum master decide which user stories to complete within the sprint.
C. Have the team decide which user stories to complete within the sprint.
D. Order the user stories by their story points. Select the top stories based on the team’s velocity.
Answer: C
Explanation: The Sprint is a fixed-length event (30 days or less) in which the Development Team forecasts items from the Product Backlog and develops the items in the Sprint Backlog according to the acceptance criteria and their Definition of “Done.”
Professional Scrum Development with Microsoft Visual Studio 2012 p.169
Q45. - (Topic 1)
Your network environment is configured according to the following table:
The data tier is configured to use SQL Server Reporting Services (SSRS) and SQL Server Analysis Services (SSAS). The data tier currently does not contain a database named TFS_Analysis.
You need to rebuild the data warehouse, including the SSRS and SSAS databases.
What should you do?
A. Log on to the application-tier server, then rebuild and redeploy the data warehouse cube by using SQL Server Business Intelligence Studio.
B. Log on to the application-tier server and run the TFSConfig.exe Rebuild Warehouse /analysisServices / ReportingDataSourcePassword: <password> command.
C. Log on to the application-tier server. From the Reporting node in the TFS Administration Console, select the Start Rebuild option.
D. Log on to the database-tier server and rebuild the data warehouse using SQL Server Management Studio.
E. Log on to the database-tier server, then rebuild and redeploy the data warehouse cube by using SQL Server Business Intelligence Studio.
Answer: C
Q46. - (Topic 1)
Your client’s network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server installed at its main office.
The network administrator at a remote office reports high WAN utilization. Users at the remote office report slow response times when downloading source code.
You need to minimize WAN utilization and improve the response times for downloading source code.
What should you do?
A. Install TFS Server at the remote site and set up database synchronization between the existing TFS Server and the remote site.
B. Install and configure TFS Proxy at the remote site. Point the TFS Proxy to the TFS server and point Team Explorer to the TFS Proxy.
C. Install and configure IIS caching. Point Team Explorer to the IIS server.
D. Install TFS Proxy at the remote site. Configure TFS Proxy to point to the TFS Server and configure each user’s Visual Studio Source Control to use the proxy server for file downloads.
Answer: D
Q47. DRAG DROP - (Topic 1)
Your team uses Microsoft Visual Studio Team Foundation Server (TFS) to manage automated builds.
You want to change the drop location of a build definition during a single execution of the build. All subsequent builds for that definition should use the drop location currently defined.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Q48. - (Topic 2)
You are using Microsoft Test Manager (MTM).
You plan to reduce the maintenance of test suites.
You need to create test suites for which the test cases are automatically added.
What are two possible types of test suites that achieve this goal? (Each correct answer
presents a complete solution. Choose two.)
A. Exploratory-based
B. Static
C. Query-based
D. Requirements-based
Answer: C,D
Q49. - (Topic 2)
You are using Microsoft Test Manager (MTM).
You have a shared steps work item that you want to hide in the Shared Steps Manager.
You need to ensure that only active shared steps work items are displayed.
What should you do?
A. Change the state of the shared steps work item to Closed, then customize the filter of the Shared Steps Manager view to display shared steps that have the status Active.
B. Delete the shared steps work item from all test cases where it is used, then delete the shared steps work item from the Shared Steps Manager.
C. For the shared steps work item, change the Show in Shared Step Manager setting to Do Not Show.
D. Change the state of the shared steps work item to Removed.
Answer: A
Q50. - (Topic 3)
You manage a project that has three teams working in parallel on a single codebase using a Scrum process methodology.
You need to ensure that each team can manage work separately while editing a shared code base.
What should you do?
A. Within a single team project, create separate iteration paths for each team. Assign each team member to their respective iteration path.
B. Create a team project for each team, assigning different team members to each team project.
C. Within a single team project, create three teams. Assign each team member to their respective teams.
D. Create a team project for each team, assigning all team members to each team project.
Answer: C