It is impossible to pass IBM C2010-825 exam without any help in the short term. Come to Pass4sure soon and find the most advanced, correct and guaranteed IBM C2010-825 practice questions. You will get a surprising result by our Renovate IBM Certified Solutions Specialist - Rational Team Concert V6 practice guides.
Free C2010-825 Demo Online For IBM Certifitcation:
NEW QUESTION 1
What is the source of the data to create metric based reports?
Answer: B
NEW QUESTION 2
A user needs to import work items into a project area using the RTC Eclipse client. Which file content type can be used?
Answer: C
NEW QUESTION 3
Management is asking for report describing all RTC users, team areas, team members and corresponding process roles, as well as team area administrators for an RTC project area.
How should the report be created?
Answer: D
NEW QUESTION 4
An RTC administrator has installed JTS and CCM using a departmental server topology and completed the Jazz Team Server and Application Setup process.
How many Public URIs (context root) exist for this topology?
Answer: C
NEW QUESTION 5
A developer is working on source code changes and would like to test them using an existing build definition. The developer, however, does not want the testing to impact the overall build definition status or notify subscribers. How can this be accomplished?
Answer: A
NEW QUESTION 6
A scrum master wants to determine if the team has enough time to complete the work planned for an iteration. What is used to assess this?
Answer: B
NEW QUESTION 7
A development has organized the source code into components and found that there is a strong dependency or containment relationship between two of the components.
What action could the development team take to establish this relationship?
Answer: B
NEW QUESTION 8
An administrator would like to prevent source code check-ins without a review and has added the Code Review Summary to the work item editor presentation.
What additional step must be taken?
Answer: B
NEW QUESTION 9
A project manager wants to create an effective project dashboard and is planning the content. Which points should be considered? (Choose three.)
Answer: BEF
NEW QUESTION 10
A developer working in the RTC Eclipse client has changed several files in the loaded workspace and checked them in. The developer then suspends the changes.
What is the result?
Answer: C
NEW QUESTION 11
A project manager determines the current iteration is complete and decides that the next iteration should be started. How is this done?
Answer: B
NEW QUESTION 12
Which RTC client allows a user to lock and download a source file in a single operation?
Answer: A
NEW QUESTION 13
A user wants a query to filter work items in the closed group of a workflow. Which option in the query condition allows this?
Answer: C
NEW QUESTION 14
A development team is using the RTC web interface to update plans and work items. One user notices that recent work item changes are not rendered in the web browser.
What is the reason for this?
Answer: A
NEW QUESTION 15
A user wants to create an enumeration. There is a requirement to allow users with the appropriate permissions to add new literals from the Work Item editor.
Where does the enumeration need to be stored?
Answer: A
NEW QUESTION 16
An administrator wants to make sure that time remaining on work items in a plan view are consistent with the estimate. Which plan check ensures this?
Answer: B
NEW QUESTION 17
A user loaded a repository workspace that flows with the team's stream. The user can see an incoming change for the file CoreClass in the RTC client, but decides to edit this file and check in the change.
How does the Jazz SCM handle this situation?
Answer: D
NEW QUESTION 18
A scrum master has defined an iteration plan and created several tasks for the plan. The assigned team members are updating the tasks' attributes of Status, Estimate Correction and Time Remaining in the work item editors.
How do these updates affect the plan's Work Breakdown view?
Answer: A
NEW QUESTION 19
A user wants to add widgets from external sources to a RTC Dashboard. Which type can be added?
Answer: A
NEW QUESTION 20
A developer has been assigned the following roles, in order, for the project area:
• Team Member
• Stakeholder
and the following roles, in order, for the team area:
1. Release Engineer
2. Developer
Deliver preconditions have been configured for the team area.
Which role is considered first during the deliver operation to a stream owned by the team area?
Answer: B
NEW QUESTION 21
A user needs to export the results from a work item query in the RTC Eclipse client. Which of the below file formats can be used?
Answer: C
NEW QUESTION 22
Which build artifact allows developers to associate the outcome with a release?
Answer: B
NEW QUESTION 23
......
Recommend!! Get the Full C2010-825 dumps in VCE and PDF From Downloadfreepdf.net, Welcome to Download: https://www.downloadfreepdf.net/C2010-825-pdf-download.html (New 60 Q&As Version)